Using TEA with Existing Tests (Brownfield) Apply TEA workflows to legacy codebases with existing test suites

Using TEA with Existing Tests (Brownfield)

Use TEA on brownfield projects (existing codebases with legacy tests) to establish coverage baselines, identify gaps, and improve test quality without starting from scratch.

When to Use This

  • Existing codebase with some tests already written
  • Legacy test suite needs quality improvement
  • Adding features to existing application
  • Need to understand current test coverage
  • Want to prevent regression as you add features

Prerequisites

  • BMad Method installed
  • TEA agent available
  • Existing codebase with tests (even if incomplete or low quality)
  • Tests run successfully (or at least can be executed)

Note: If your codebase is completely undocumented, run *document-project first to create baseline documentation.

Brownfield Strategy

Phase 1: Establish Baseline

Understand what you have before changing anything.

Step 1: Baseline Coverage with *trace

Run *trace Phase 1 to map existing tests to requirements:

*trace

Select: Phase 1 (Requirements Traceability)

Provide:

  • Existing requirements docs (PRD, user stories, feature specs)
  • Test location (tests/ or wherever tests live)
  • Focus areas (specific features if large codebase)

Output: traceability-matrix.md showing:

  • Which requirements have tests
  • Which requirements lack coverage
  • Coverage classification (FULL/PARTIAL/NONE)
  • Gap prioritization

Example Baseline:

# Baseline Coverage (Before Improvements)

**Total Requirements:** 50
**Full Coverage:** 15 (30%)
**Partial Coverage:** 20 (40%)
**No Coverage:** 15 (30%)

**By Priority:**
- P0: 50% coverage (5/10) ❌ Critical gap
- P1: 40% coverage (8/20) ⚠️ Needs improvement
- P2: 20% coverage (2/10) ✅ Acceptable

This baseline becomes your improvement target.

Step 2: Quality Audit with *test-review

Run *test-review on existing tests:

*test-review tests/

Output: test-review.md with quality score and issues.

Common Brownfield Issues:

  • Hard waits everywhere (page.waitForTimeout(5000))
  • Fragile CSS selectors (.class > div:nth-child(3))
  • No test isolation (tests depend on execution order)
  • Try-catch for flow control
  • Tests don't clean up (leave test data in DB)

Example Baseline Quality:

# Quality Score: 55/100

**Critical Issues:** 12
- 8 hard waits
- 4 conditional flow control

**Recommendations:** 25
- Extract fixtures
- Improve selectors
- Add network assertions

This shows where to focus improvement efforts.

Phase 2: Prioritize Improvements

Don't try to fix everything at once.

Focus on Critical Path First

Priority 1: P0 Requirements

Goal: Get P0 coverage to 100%

Actions:
1. Identify P0 requirements with no tests (from trace)
2. Run *automate to generate tests for missing P0 scenarios
3. Fix critical quality issues in P0 tests (from test-review)

Priority 2: Fix Flaky Tests

Goal: Eliminate flakiness

Actions:
1. Identify tests with hard waits (from test-review)
2. Replace with network-first patterns
3. Run burn-in loops to verify stability

Example Modernization:

Before (Flaky - Hard Waits):

test('checkout completes', async ({ page }) => {
  await page.click('button[name="checkout"]');
  await page.waitForTimeout(5000);  // ❌ Flaky
  await expect(page.locator('.confirmation')).toBeVisible();
});

After (Network-First - Vanilla):

test('checkout completes', async ({ page }) => {
  const checkoutPromise = page.waitForResponse(
    resp => resp.url().includes('/api/checkout') && resp.ok()
  );
  await page.click('button[name="checkout"]');
  await checkoutPromise;  // ✅ Deterministic
  await expect(page.locator('.confirmation')).toBeVisible();
});

After (With Playwright Utils - Cleaner API):

import { test } from '@seontechnologies/playwright-utils/fixtures';
import { expect } from '@playwright/test';

test('checkout completes', async ({ page, interceptNetworkCall }) => {
  // Use interceptNetworkCall for cleaner network interception
  const checkoutCall = interceptNetworkCall({
    method: 'POST',
    url: '**/api/checkout'
  });

  await page.click('button[name="checkout"]');

  // Wait for response (automatic JSON parsing)
  const { status, responseJson: order } = await checkoutCall;

  // Validate API response
  expect(status).toBe(200);
  expect(order.status).toBe('confirmed');

  // Validate UI
  await expect(page.locator('.confirmation')).toBeVisible();
});

Playwright Utils Benefits:

  • interceptNetworkCall for cleaner network interception
  • Automatic JSON parsing (responseJson ready to use)
  • No manual await response.json()
  • Glob pattern matching (**/api/checkout)
  • Cleaner, more maintainable code

For automatic error detection, use network-error-monitor fixture separately. See Integrate Playwright Utils.

Priority 3: P1 Requirements

Goal: Get P1 coverage to 80%+

Actions:
1. Generate tests for highest-risk P1 gaps
2. Improve test quality incrementally

Create Improvement Roadmap

# Test Improvement Roadmap

## Week 1: Critical Path (P0)
- [ ] Add 5 missing P0 tests (Epic 1: Auth)
- [ ] Fix 8 hard waits in auth tests
- [ ] Verify P0 coverage = 100%

## Week 2: Flakiness
- [ ] Replace all hard waits with network-first
- [ ] Fix conditional flow control
- [ ] Run burn-in loops (target: 0 failures in 10 runs)

## Week 3: High-Value Coverage (P1)
- [ ] Add 10 missing P1 tests
- [ ] Improve selector resilience
- [ ] P1 coverage target: 80%

## Week 4: Quality Polish
- [ ] Extract fixtures for common patterns
- [ ] Add network assertions
- [ ] Quality score target: 75+

Phase 3: Incremental Improvement

Apply TEA workflows to new work while improving legacy tests.

For New Features (Greenfield Within Brownfield)

Use full TEA workflow:

1. *test-design (epic-level) - Plan tests for new feature
2. *atdd - Generate failing tests first (TDD)
3. Implement feature
4. *automate - Expand coverage
5. *test-review - Ensure quality

Benefits:

  • New code has high-quality tests from day one
  • Gradually raises overall quality
  • Team learns good patterns

For Bug Fixes (Regression Prevention)

Add regression tests:

1. Reproduce bug with failing test
2. Fix bug
3. Verify test passes
4. Run *test-review on regression test
5. Add to regression test suite

For Refactoring (Regression Safety)

Before refactoring:

1. Run *trace - Baseline coverage
2. Note current coverage %
3. Refactor code
4. Run *trace - Verify coverage maintained
5. No coverage should decrease

Phase 4: Continuous Improvement

Track improvement over time.

Quarterly Quality Audits

Q1 Baseline:

Coverage: 30%
Quality Score: 55/100
Flakiness: 15% fail rate

Q2 Target:

Coverage: 50% (focus on P0)
Quality Score: 65/100
Flakiness: 5%

Q3 Target:

Coverage: 70%
Quality Score: 75/100
Flakiness: 1%

Q4 Target:

Coverage: 85%
Quality Score: 85/100
Flakiness: <0.5%

Brownfield-Specific Tips

Don't Rewrite Everything

Common mistake:

"Our tests are bad, let's delete them all and start over!"

Better approach:

"Our tests are bad, let's:
1. Keep tests that work (even if not perfect)
2. Fix critical quality issues incrementally
3. Add tests for gaps
4. Gradually improve over time"

Why:

  • Rewriting is risky (might lose coverage)
  • Incremental improvement is safer
  • Team learns gradually
  • Business value delivered continuously

Use Regression Hotspots

Identify regression-prone areas:

## Regression Hotspots

**Based on:**
- Bug reports (last 6 months)
- Customer complaints
- Code complexity (cyclomatic complexity >10)
- Frequent changes (git log analysis)

**High-Risk Areas:**
1. Authentication flow (12 bugs in 6 months)
2. Checkout process (8 bugs)
3. Payment integration (6 bugs)

**Test Priority:**
- Add regression tests for these areas FIRST
- Ensure P0 coverage before touching code

Quarantine Flaky Tests

Don't let flaky tests block improvement:

// Mark flaky tests with .skip temporarily
test.skip('flaky test - needs fixing', async ({ page }) => {
  // TODO: Fix hard wait on line 45
  // TODO: Add network-first pattern
});

Track quarantined tests:

# Quarantined Tests

| Test                | Reason                     | Owner    | Target Fix Date |
| ------------------- | -------------------------- | -------- | --------------- |
| checkout.spec.ts:45 | Hard wait causes flakiness | QA Team  | 2026-01-20      |
| profile.spec.ts:28  | Conditional flow control   | Dev Team | 2026-01-25      |

Fix systematically:

  • Don't accumulate quarantined tests
  • Set deadlines for fixes
  • Review quarantine list weekly

Migrate One Directory at a Time

Large test suite? Improve incrementally:

Week 1: tests/auth/

1. Run *test-review on auth tests
2. Fix critical issues
3. Re-review
4. Mark directory as "modernized"

Week 2: tests/api/

Same process

Week 3: tests/e2e/

Same process

Benefits:

  • Focused improvement
  • Visible progress
  • Team learns patterns
  • Lower risk

Document Migration Status

Track which tests are modernized:

# Test Suite Status

| Directory          | Tests | Quality Score | Status        | Notes          |
| ------------------ | ----- | ------------- | ------------- | -------------- |
| tests/auth/        | 15    | 85/100        | ✅ Modernized  | Week 1 cleanup |
| tests/api/         | 32    | 78/100        | ⚠️ In Progress | Week 2         |
| tests/e2e/         | 28    | 62/100        | ❌ Legacy      | Week 3 planned |
| tests/integration/ | 12    | 45/100        | ❌ Legacy      | Week 4 planned |

**Legend:**
- ✅ Modernized: Quality >80, no critical issues
- ⚠️ In Progress: Active improvement
- ❌ Legacy: Not yet touched

Common Brownfield Challenges

"We Don't Know What Tests Cover"

Problem: No documentation, unclear what tests do.

Solution:

1. Run *trace - TEA analyzes tests and maps to requirements
2. Review traceability matrix
3. Document findings
4. Use as baseline for improvement

TEA reverse-engineers test coverage even without documentation.

"Tests Are Too Brittle to Touch"

Problem: Afraid to modify tests (might break them).

Solution:

1. Run tests, capture current behavior (baseline)
2. Make small improvement (fix one hard wait)
3. Run tests again
4. If still pass, continue
5. If fail, investigate why

Incremental changes = lower risk

"No One Knows How to Run Tests"

Problem: Test documentation is outdated or missing.

Solution:

1. Document manually or ask TEA to help analyze test structure
2. Create tests/README.md with:
   - How to install dependencies
   - How to run tests (npx playwright test, npm test, etc.)
   - What each test directory contains
   - Common issues and troubleshooting
3. Commit documentation for team

Note: *framework is for new test setup, not existing tests. For brownfield, document what you have.

"Tests Take Hours to Run"

Problem: Full test suite takes 4+ hours.

Solution:

1. Configure parallel execution (shard tests across workers)
2. Add selective testing (run only affected tests on PR)
3. Run full suite nightly only
4. Optimize slow tests (remove hard waits, improve selectors)

Before: 4 hours sequential
After: 15 minutes with sharding + selective testing

How *ci helps:

  • Scaffolds CI configuration with parallel sharding examples
  • Provides selective testing script templates
  • Documents burn-in and optimization strategies
  • But YOU configure workers, test selection, and optimization

With Playwright Utils burn-in:

"We Have Tests But They Always Fail"

Problem: Tests are so flaky they're ignored.

Solution:

1. Run *test-review to identify flakiness patterns
2. Fix top 5 flaky tests (biggest impact)
3. Quarantine remaining flaky tests
4. Re-enable as you fix them

Don't let perfect be the enemy of good

Brownfield TEA Workflow

1. Documentation (if needed):

*document-project

2. Baseline (Phase 2):

*trace Phase 1 - Establish coverage baseline
*test-review - Establish quality baseline

3. Planning (Phase 2-3):

*prd - Document requirements (if missing)
*architecture - Document architecture (if missing)
*test-design (system-level) - Testability review

4. Infrastructure (Phase 3):

*framework - Modernize test framework (if needed)
*ci - Setup or improve CI/CD

5. Per Epic (Phase 4):

*test-design (epic-level) - Focus on regression hotspots
*automate - Add missing tests
*test-review - Ensure quality
*trace Phase 1 - Refresh coverage

6. Release Gate:

*nfr-assess - Validate NFRs (if enterprise)
*trace Phase 2 - Gate decision

Workflow Guides:

Customization:

Understanding the Concepts

Reference