# Change Navigation Checklist **Purpose:** To systematically guide the selected Agent and user through the analysis and planning required when a significant change (pivot, tech issue, missing requirement, failed story) is identified during the BMAD workflow. **Instructions:** Review each item with the user. Mark `[x]` for completed/confirmed, `[N/A]` if not applicable, or add notes for discussion points. --- ## 1. Understand the Trigger & Context - [ ] **Identify Triggering Story:** Clearly identify the story (or stories) that revealed the issue. - [ ] **Define the Issue:** Articulate the core problem precisely. - [ ] Is it a technical limitation/dead-end? - [ ] Is it a newly discovered requirement? - [ ] Is it a fundamental misunderstanding of existing requirements? - [ ] Is it a necessary pivot based on feedback or new information? - [ ] Is it a failed/abandoned story needing a new approach? - [ ] **Assess Initial Impact:** Describe the immediate observed consequences (e.g., blocked progress, incorrect functionality, non-viable tech). - [ ] **Gather Evidence:** Note any specific logs, error messages, user feedback, or analysis that supports the issue definition. ## 2. Epic Impact Assessment - [ ] **Analyze Current Epic:** - [ ] Can the current epic containing the trigger story still be completed? - [ ] Does the current epic need modification (story changes, additions, removals)? - [ ] Should the current epic be abandoned or fundamentally redefined? - [ ] **Analyze Future Epics:** - [ ] Review all remaining planned epics. - [ ] Does the issue require changes to planned stories in future epics? - [ ] Does the issue invalidate any future epics? - [ ] Does the issue necessitate the creation of entirely new epics? - [ ] Should the order/priority of future epics be changed? - [ ] **Summarize Epic Impact:** Briefly document the overall effect on the project's epic structure and flow. ## 3. Artifact Conflict & Impact Analysis - [ ] **Review PRD:** - [ ] Does the issue conflict with the core goals or requirements stated in the PRD? - [ ] Does the PRD need clarification or updates based on the new understanding? - [ ] **Review Architecture Document:** - [ ] Does the issue conflict with the documented architecture (components, patterns, tech choices)? - [ ] Are specific components/diagrams/sections impacted? - [ ] Does the technology list need updating? - [ ] Do data models or schemas need revision? - [ ] Are external API integrations affected? - [ ] **Review Frontend Spec (if applicable):** - [ ] Does the issue conflict with the FE architecture, component library choice, or UI/UX design? - [ ] Are specific FE components or user flows impacted? - [ ] **Review Other Artifacts (if applicable):** - [ ] Consider impact on deployment scripts, IaC, monitoring setup, etc. - [ ] **Summarize Artifact Impact:** List all artifacts requiring updates and the nature of the changes needed. ## 4. Path Forward Evaluation - [ ] **Option 1: Direct Adjustment / Integration:** - [ ] Can the issue be addressed by modifying/adding future stories within the existing plan? - [ ] Define the scope and nature of these adjustments. - [ ] Assess feasibility, effort, and risks of this path. - [ ] **Option 2: Potential Rollback:** - [ ] Would reverting completed stories significantly simplify addressing the issue? - [ ] Identify specific stories/commits to consider for rollback. - [ ] Assess the effort required for rollback. - [ ] Assess the impact of rollback (lost work, data implications). - [ ] Compare the net benefit/cost vs. Direct Adjustment. - [ ] **Option 3: PRD MVP Review & Potential Re-scoping:** - [ ] Is the original PRD MVP still achievable given the issue and constraints? - [ ] Does the MVP scope need reduction (removing features/epics)? - [ ] Do the core MVP goals need modification? - [ ] Are alternative approaches needed to meet the original MVP intent? - [ ] **Extreme Case:** Does the issue necessitate a fundamental replan or potentially a new PRD V2 (to be handled by PM)? - [ ] **Select Recommended Path:** Based on the evaluation, agree on the most viable path forward. ## 5. Sprint Change Proposal Components (Ensure all agreed-upon points from previous sections are captured in the proposal) - [ ] **Identified Issue Summary:** Clear, concise problem statement. - [ ] **Epic Impact Summary:** How epics are affected. - [ ] **Artifact Adjustment Needs:** List of documents to change. - [ ] **Recommended Path Forward:** Chosen solution with rationale. - [ ] **PRD MVP Impact:** Changes to scope/goals (if any). - [ ] **High-Level Action Plan:** Next steps for stories/updates. - [ ] **Agent Handoff Plan:** Identify roles needed (PM, Arch, Design Arch, PO). ## 6. Final Review & Handoff - [ ] **Review Checklist:** Confirm all relevant items were discussed. - [ ] **Review Sprint Change Proposal:** Ensure it accurately reflects the discussion and decisions. - [ ] **User Approval:** Obtain explicit user approval for the proposal. - [ ] **Confirm Next Steps:** Reiterate the handoff plan and the next actions to be taken by specific agents. ---