# Risk Governance and Gatekeeping - Score risk as probability (1–3) × impact (1–3); totals ≥6 demand mitigation before approval, 9 mandates a gate failure. - Classify risks across TECH, SEC, PERF, DATA, BUS, OPS. Document owners, mitigation plans, and deadlines for any score above 4. - Trace every acceptance criterion to implemented tests; missing coverage must be resolved or explicitly waived before release. - Gate decisions: - **PASS** – no critical issues remain and evidence is current. - **CONCERNS** – residual risk exists but has owners, actions, and timelines. - **FAIL** – critical issues unresolved or evidence missing. - **WAIVED** – risk accepted with documented approver, rationale, and expiry. - Maintain a gate history log capturing updates so auditors can follow the decision trail. - Use the probability/impact scale fragment for shared definitions when scoring teams run the matrix. _Source: Murat risk governance notes, gate schema guidance._